We install the fire protection tanks in stages. Without heavy equipment involved.
First stage is the foundation preparing for under the tank. Which is the land alignment and the pouring of the concrete slab. On this stage materials necessary for the tank construction are delivered to the construction site.
When the land is ready and all the tank elements are in place, our employees start the installation. We install the tank with the hydraulic external cylinders. Then we raise steel construction and install internal isolation. We place the membranes and install the equipment. Then we install the tank with the anchors and bolts to the ground.
Up to the customer request we install the piping inside the tank and additional equipment
It’s the most important stage. First we fill the tank up to the 1,5 m level for the tightness test of the flange transitions for the process lines. On the second stage we fill up the rest of the water. Tightness test lasts 24 hours according to the norm.
On this stage we check if the electrical equipment works seamless
Immediately after finishing the earlier work stages we pass as-built documentation with the certificates and guarantee card. In the end we clean up the installation site.